Project Details

Location: PTOLEMAIS GREECE
Power Plant Capacity: 660 MW
End Customer: P.P.C. S.A.
EPC Contractor: TERNA
Turbine Manufacturer: MITSUBISHI HITACHI POWER SYSTEMS MHPSE
Start: 2017
Finish: On going
Category: ERECTION OF BOILER PRESSURE PARTS

 

Scope of Works

Complete mechanical Erection works of HRSG Boiler Pressure parts including:

  • Erection of pressure parts suspension system
  • Boiler Roof
  • Membrane walls-Vertical, Bundles, Outer supporting tubes, Connecting tubes, Headers, Spiral membrane walls, LUBECO system, buckstays, Boiler piping etc.
  • Total weight 1450tn weld joints 76000

 